The DCP4 is built to serve the New York University in Saadiyat Island, Abu Dhabi through providing chilled water to the Energy Transfer Stations within the university building. The scope of works consists of Design and Build of DCP with and ultimate capacity of 16,000TR. The contract is for phase 1 only which consists of complete civil works and building services, chiller capacity of 9,000TR and TES of 2,500TR. Phase 2 will include and additional 4,500TR chiller capacity along with its ancillaries.
The scope also includes the design, installation and commissioning of the Energy Transfer Stations and same for the chilled water network piping.