Supply, fabrication of steel structure for the Air Cooled Condenser.
The structure comprises of nearly 2000 Tons of structural steel that will be pre-fabricated and transported to site. Supply, fabrication of the low pressure steam ductwork connecting the turbine building and the ACC, along with distribution and bypass ducts. The steam duct will be in the range of 6.5 m diameter all down to 0.85 m in diameter. The duct when assembled shall be just over 700 Tons. The preassembly of the fans, motors, coils and necessary duct work to connect the ACC to the client’s steam turbine building.
The transportation and lifting of assembled modules into final position. The project is in JV partnership with technology provider.
Project Scope / Highlights
Project
Dubai Energy from Waste Project – Air Cooled Condensers
Location
Dubai Energy from Waste Project, UAE, Dubai
Year
2023
Plant Capacity
The facility will process 1.9 million tonnes of municipal waste per year, produce approximately 200 MW of renewable electricity
Development / Client
BESIX and its partners carry out one of the world’s largest waste-to-energy plants to be built in a single phase. The facility will process 1.9 million tonnes of municipal waste per year, produce approximately 200 MW of renewable electricity.